Saturday, June 23, 2007

Driveway Excavation

The old railway roadbed was several feet higher than the building site; so it had to be brought down to the level of the yard area. The railbed was full of rocks and this turned out to be a huge job. Some of the larger boulders took almost an entire day to dislodge and move.


Note the large boulder in the left foreground. This sucker is still there, I never did get it out.






This one was way too big to fit into the front-end loader. All I could do was roll it to a low spot in the yard.

Thursday, June 14, 2007

Rough Site Work Completed

The building site is pretty much cleared now. Excavation for the basement can begin anytime.